AHR SECTORS
HEALTH

ST JAMES'S UNIVERSITY HOSPITAL


  • AS PART OF OUR FRAMEWORK AGREEMENT WITH LEEDS TEACHING HOSPITALS NHS TRUST, AHR BUILDING CONSULTANCY WAS APPOINTED TO CARRY OUT REFURBISHMENT WORKS TO THE EXTERNAL FABRIC OF THE HISTORIC GRADE II LISTED LINCOLN WING A BLOCK.

  • The Practice was appointed after debris started to fall off the building and scaffolding had to be put up as a temporary measure. A key requirement was to ensure that the works were carried out to the best workmanship standards to prevent the repeat of falling debris upon completion. Work included brickwork re-pointing, and repairs to stone copings, stone pierced parapets, and high-level chimneys.

DOWNLOADS

PEOPLE

NEWS
  • Cornwall Innovation Centres Praised by Secretary of State

  • 30 SEPTEMBER 2014

  • READ MORE >

ALLAN HUNT

Director

HELEN REVITT

Regional
Director

  • EDUCATION

  • SECTOR >

KIRKLEES COUNCIL LEISURE SERVICES

CLEVELAND CLINIC